Winning a federal grant or an SBIR award is a big moment, and it's also the start of a new set of obligations for your finance team. The money comes with written rules about how you track it, document it and prove it was spent the way the award says. And every one of those rules assumes someone in your finance team reviews the books before a reviewer from the government ever does.
We see two kinds of companies in this position. The first set up their books for the award before the first dollar landed. The second find out what the rules require when an agency asks for support, and spend weeks rebuilding records they could have kept in an afternoon over the course of a month. The difference between them is mostly controllership.
Federal grants and cooperative agreements generally fall under the Uniform Guidance in 2 CFR Part 200. Nonprofits, universities and state and local governments live under it directly, and agencies can extend parts of it to for-profit recipients through the terms of the award, so read your award letter closely.
Federal contracts, including most Department of Defense SBIR and STTR awards, follow the Federal Acquisition Regulation, and the Defense Contract Audit Agency is usually the reviewer. The two systems use different language, and they ask for a lot of the same things.
The financial management section of the Uniform Guidance, 2 CFR 200.302, lists what a recipient's accounting system has to do. In plain terms:
The next section, 200.303, requires recipients to "establish, document, and maintain effective internal control over the Federal award," and to take prompt action when they find noncompliance.
Payroll is where most organizations get tripped up. Under 2 CFR 200.430(g), charges for salaries and wages "must be based on records that accurately reflect the work performed." Budget estimates alone don't qualify. If you charge payroll to an award based on an estimate during the year, the rule requires "periodic after-the-fact reviews of interim charges" and adjustments so the final amount is "accurate, allowable, and properly allocated." That's a controller review, written into federal regulation.
I saw this firsthand as interim controller for a nonprofit running 3 federal grants and a state contract. All year, payroll had been charged to the awards straight from the budget: 60% of the program director's salary to one grant, 40% to another. Nobody had compared that split to what she worked on. When we lined her charges up against her calendar and program reports, the real split was closer to 30/70, and one grant had absorbed about $38,000 of salary that belonged to the other. We made the adjustment before the auditors arrived, then put a quarterly after-the-fact review process in place to ensure the records remain accurate and audit-ready ongoing into the future. The initial reconciliation and cleanup work took quite a bit of time, but the new quarterly review only takes a few minutes each quarter now.
For nonprofits and other non-federal entities, the stakes rise at a specific number. Under 2 CFR 200.501, an organization that spends $1,000,000 or more in federal awards during its fiscal year needs a single audit for that year. Below that threshold you're exempt from the federal audit requirement, and your records still have to be available for review by the agency, the pass-through entity and the Government Accountability Office.
Defense and research founders run into this at Phase II, when awards get larger and often shift from fixed-price to cost-reimbursement. The SBIR program's own accounting tutorial explains that many agencies (NIH and NSF are the stated exceptions) rely on the Defense Contract Audit Agency for a pre-award survey of your accounting system, built around ten requirements from Standard Form 1408.
DCAA reports seeing the most errors in four of those ten:
The tutorial is direct about timekeeping. Timesheets have to be kept by everyone in the company, "even if they are the president or CEO," entries have to be made daily, and each contract or grant gets its own line. Without that, you can't support the indirect rate that recovers a big part of your overhead – the CEO's time spent running the company, writing proposals and managing the business is often the largest piece of it.
One of the first SBIR clients I worked with was a 12-person engineering firm heading into a cost-reimbursement Phase II. The engineers filled out timesheets. The CEO didn't, on the theory that he was always working, so none of his time was documented. His salary was the biggest single cost in the overhead pool, and without timesheets there was no way to prove how much of it belonged there and how much belonged on the contracts. We gave him the same daily timesheet as everyone else, with separate lines for each contract, proposal writing and general management. After 2 months there was enough history to support the indirect rate in the proposal. He still grumbles about timesheets every Friday, but he does fill them out consistently now!
A bank feed can tell you that payroll went out on the 15th. It can't tell you which award each hour belongs to, whether the team dinner on the company card is an entertainment cost the government won't reimburse (2 CFR 200.438 treats most entertainment as unallowable), or whether this month's spending on Award A has drifted past its budget. Those are judgment calls made against the award terms, and they need to be made every month, while the receipts and the people who incurred the costs are still easy to find.
On the engagements where we handle this, the monthly close for a company with federal awards looks something like this:
It's ordinary controllership pointed at the specific questions a federal reviewer is going to ask, and it's far cheaper to do monthly than to reconstruct under a deadline.
At Meals on Wheels West, auditor time on-site dropped to one day from the two or three it used to take. At the Santa Monica Chamber of Commerce, one grant runs to $300,000 with three vendors under a single contract, and our team handles the invoicing behind it – the kind of arrangement that only holds up with clean award-level tracking.
If you're applying for a federal grant or an SBIR Phase II this year, our advice is to set up the books for it before the award is received. Decide how costs will be tagged to each award, put a daily timekeeping system in place for everyone, separate unallowable costs from day one, and agree on who reviews the close each month. If you already have awards and you're not sure your records would hold up, let's look at them together before someone else does.
This is Part 2 of our four-part series, Controllership and the people counting on it: